- Facilitation and guidance in the planning process by Lt. Gen. (Ret.) Thad Wolfe
- September 2016: Strategic Planning Meeting with Board of Directors
- Informed by previous work already in progress and Admin Team input
- Determined Vision and Goals
- Continuous: Bi-weekly meetings with the Executive Director, Elementary Principal, Operations Director, and Business Manager
- Determined supporting objectives
- Assigned ownership of each objective
- Have begun work on those objectives
- Have begun work synchronizing the accomplishment of the objectives
![StrategicPlaningProcessGraphic](https://thevanguardschool.com/wp-content/uploads/2019/05/StrategicPlaningProcessGraphic.png)
Recent Accomplishments
-
- August 2015-2016: Comprehensive policy review by the Board
- April 2016: Completed refinance in preparation to build new junior high building
- Summer 2016: Moved fourth grade to Corona Campus
- Summer 2016: Moved kindergarten into the main K-3 building
- October 2016: Broke ground on the new junior high building
- December 2016: Emergency Operations Plan (EOP) completed, presented, and Board-approved
- March 2017: New junior high dome inflated